Hydropower Abstraction Licensing
Hydropower Abstraction Licensing
Understand the legal requirements for hydropower in the United Kingdom
hydro
The
water supply is limited and must be protected by law to stop people from diverting streams and rivers, polluting, or taking large quantities of water from them for their own personal use to the detriment of others or the environment. Anyone who takes more than 4,000 gallons of water per day from a river or stream needs to obtain a licence from the
Environment Agency.
Since a
waterwheel or any other
hydropower generator temporarily diverts free flowing water, such an
Abstraction Licence must be obtained.
Why is Hydropower not Exempt
Although
hydropower offers many environmental benefits, it can also have serious negative effects if care is not taken. Oils and greases used in maintenance of a hydropower generator could
pollute the water, the movements of
fish can be limited and they and other life can be killed by turbines. Finally, hydropower systems can affect land drainage and potentially increase the risk of flooding.
What is an Abstraction Licence
An
Abstraction Licence gives the holder the right to take a fixed amount of water daily from a particular inland or underground water source for a time-limited period (usually 12 years).
After 12 years the licencee must reapply proving that they still need the water, that the water taken has been used efficiently, and that there have not been negative effects to the environment caused by the abstraction.
Abstraction Licence Costs
When applying for an
abstraction licence an
application charge of £135 (at time of writing) is payable together with any private consultancy fees, statutory advertising, and other costs incurred by the
Environment Agency in processing the application.
There is also a
subsistence charge payable on 1st April each year which depends on a number of factors: the
volume of water to be taken, the
source of the water, the
season in which it is taken, the
loss (a measure of how much water is wasted), and the UK
region.
Calculating Annual Abstraction Licence Costs
Annual Charge |
= SUC x Volume x Source x Season x Loss |
SUC
Each UK region is given a
Standard Unit Charge - from £24.86 per 1,000 cubic metres (*) of water per year for Northumbria, down to just £10.71 per 1,000 cubic meters per year for Yorkshire.
(*)
1,000 cubic metres of water is equivalent to just under 220,000 gallons.
Volume
The amount of water licenced to be abstracted each year (measured in units of 1,000 cubic metres).
Source
The
Source Factor is determined by the origin of the water - for example, 0.2 for tidal water, 1.0 for groundwater.
Season
Water is far more scarce in the summer than in the winter, therefore the
Season Factor for summer (1.6) is ten times that for winter (0.16). If water is to be taken all year, the season factor is 1.0.
Loss
The
Loss Factor is used to take into account how much water is lost because it was abstracted - for example, crop spraying leads to heavy losses, but large scale
hydropower plants lead to minimal losses. Hence the loss factor for 5MW+ hydropower plants is just 0.003 compared to 1.0 for crop spraying. Abstraction for domestic size hydropower generation is considered to be
low loss and so has a
loss factor of 0.03.
These costs are all explained in far greater detail in the
Environment Agency Scheme of Abstraction Charges (PDF) document which can be viewed here.
Further Information
The Environment Agency provide a selection of
Abstraction Licence guides. The main one is
Abstracting Water - A Guide to Getting Your Licence (1MB PDF) which is not a bad introduction.
Of more use is:
Hydropower - A Handbook for Agency Staff (326KB MS Word Doc) - a guide prepared to advise Environment Agency staff considering
hydropower proposals.
If you would like to contact the Environment Agency directly to ask about a planned
hydropower system you can email
enquiries@environment-agency.gov.uk or call
08705 506506.
If the complexity and cost of going through this process for a one-off single
hydropower project is daunting, there are experts out there who can do all the work for you as a comprehensive service. Try
Hydro Generation a division of Segen Ltd and (at the time of writing) the only UK company to have full accreditation under the
Low Carbon Buildings Programme for
micro-hydro installations.
Article Last Modified: 13:13, 3rd May 2007Comment on this Article
If you have any comments on this article, please email them to
neil@reuk.co.uk.
Recommended Related Articles
People who read this article also enjoyed the following articles:
Introduction to Hydro Electric PowerA brief introduction to Hydroelectic power generation
Article Last Modified: 16:37, 18th Jul 2007hydroCalculation of Hydro PowerWork out how much hydro power can be taken from flowing water with our new online automatic hydro-power calculator
Article Last Modified: 12:47, 10th Mar 2008hydro | educationPico Hydro PowerFind out more about Pico Hydro power (sub-5kW generators)
Article Last Modified: 14:35, 3rd Jan 2007hydroRun of River Hydro PowerHydro electricity generation without a dam
Article Last Modified: 14:35, 3rd Jan 2007hydroIntroduction to Water WheelsFind out more about using the power of a waterwheel
Article Last Modified: 10:16, 12th Nov 2008hydroMake a Simple Battery Status MonitorMonitor battery status with this easy electric circuit project - no skill required!
Article Last Modified: 12:33, 16th Mar 2007storage | electric circuitPermanent Magnet GeneratorBuild a wind or water power system with around a PM Generator
Article Last Modified: 11:44, 21st Jul 2008wind | hydroRainbow Power 300W Hydro Generator300 Watt 12/24 Volt hydro power generators from Rainbow Power
Article Last Modified: 15:09, 25th Jan 2007hydro | shoppingElectricity from WaterwheelsHow to generate electricity from a waterwheel
Article Last Modified: 14:12, 27th Mar 2006hydroThree Gorges DamLearn about the world's largest dam and hydro electric project
Article Last Modified: 12:03, 3rd Jan 2007hydro